Jira Based Project Planning Tools

JirabasierteProjektplanung

Our team of experts have checked various Jira PlugIns with a WBS (Work-Breakdown-Structure) for necessary key functions that are needed. We would like to present the results of this evaluation in this blog post.

Introduction

For our customer transformation program we have the following Jira plug-ins, which allow the creation of a WBS (work breakdown structure or work breakdown structure)with more than 3500 planning work packages (detailed work packages will be refined later) enable, tested in detail.

Big Gantt (as part of Big Picture):

https://marketplace.atlassian.com/apps/1213016/biggantt-gantt-chart-for-jira?hosting=cloud&tab=overview

WBS Gantt Chart:

https://marketplace.atlassian.com/apps/1211768/wbs-gantt-chart-for-jira?hosting=cloud&tab=overview

Structure Gantt:

https://marketplace.atlassian.com/apps/1217809/structure-gantt-planning-at-scale?hosting=datacenter&tab=overview

Based on the feedback on more than 30 project managers we identified several key capabilities we need in our customer context. We assigned the coverage grade of every tool to the capability to find out the tool we will use for our whole IT project portfolio: WBS Gantt Chart.

In the next section we show the result of our evaluation (it must be noted that the evaluation was already two years ago and therefore some data is not up to date. We are already working on a more up-to-date evaluation):

Result of the evaluation

Create and Maintain a WBS/Project Plan including all Elements: WBS Levels, Work packages, Activities

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
100%

Allow Users to convert a task to a milestone (Visualised as milestone) and to flag a task as inbound/outbound deliverable

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
100%

Create and maintain a hierarchical relationship in the WBS without Level limitation

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT (Limited to 10, according to vendor. 3 levels recommended).
Limited to 10 0%

Allow a full collaborative work wise for all wbs tasks and for different user access rights (Write / Read)

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
100%

Allow a full collaborative work wise for all wbs tasks and for different user access rights (Write / Read)

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
100%

Allow sub-stream related WBS plans and a master view referencing to sub-stream Plans. This Setup should be changeable. This setup should be changeable.

BIG GANT
0%
WBS GANTT CHART
80%

Technically possible. The Vendor recommends to edit a wbs task only in one gantt board (sub-stream Board). Therefore the master board should be only for reading and could have several root elements. The provider recommends to edit a wbs task only in a Gantt board (sub-stream board). Therefore, the master board should be read-only and could have multiple root elements.

STRUCTURE GANTT
100%

Visualise the Plan in List View with full customisable Columns

BIG GANT
100%
WBS GANTT CHART
80%

Sorting of several plug-In standard columns cannot be changed

STRUCTURE GANTT
100%

Visualise the WBS Plan in Gantt View with customisable Date Ranges

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
100%

Editing in Gantt AND List are possible and lead to the same data result.

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
50%

Gantt changes don’t lead always to the expected data change result.

Implementing and Visualizing a Dependency Type: From End to Start

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
100%

Implement and Visualise dependency type: FF, SF, SS

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
100%

Allow multiple dependencies between WBS Plan elements

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
100%

100% Automatic recalculation of the date due to changes in dependencies.

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
100%

Selective automatic date re-calculation based on changes of dependencies

BIG GANT
100%

Tasks can be selectively configured to recalculate automatically or manually.
Some tasks can be frozen for every normal users i.e. program key mile stones. In this case, linked WBS elements cannot force a recalculation/shift on those.

WBS GANTT CHART
100%
STRUCTURE GANTT
0%

Selective automatic date Re-calculation based on Day Lags (e.g. FS + xx Days)

BIG GANT
100%
WBS GANTT CHART
0%
STRUCTURE GANTT
0%

Lock plan elements / milestones against changing

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
0%

WBS list view allows quick inline editing in, without opening jira edit forms

BIG GANT
10%

Summary is editable.
100% planned in the product roadmap

WBS GANTT CHART
100%
STRUCTURE GANTT
100%

Allow baseline: 1…n

BIG GANT
50%
WBS GANTT CHART
50%
STRUCTURE GANTT
0%

GANTT View allows grouping the dates of child elements and showing the aggregated duration, earliest and latest Date

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
100%

Start/end date and duration of subordinate WBS elements should be aggregated bottom-up

BIG GANT
100%

Child Elements can influence directly start and end dates of upper elements, if upper elements are not locked.
If upper elemens are locked for recalculation, then changes at child elements will be limited within the range of upper elements.

WBS GANTT CHART
100%
STRUCTURE GANTT
0%

Calculation implemented by an own implemented jira script, running every 60 MIN.

Changes of start / end dates und duration should be calculated top-down to child wbs elements

BIG GANT
100%
WBS GANTT CHART
50%

simple reschedules of parent elements work as expected

STRUCTURE GANTT
0%

Expand / Reduce Plan List View to different Levels

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
100%

Add Jira Filters to WBS View allowing Sub-Set Views and Editing for Sub-Teams

BIG GANT
100%
WBS GANTT CHART
0%
STRUCTURE GANTT
100%

The Plan and all relationsships must be technically readable to allow QA Dashboards, Reporting and EVA Calculation

BIG GANT
0%
WBS GANTT CHART
100%
STRUCTURE GANTT
100%

The Plan and all relationsships must be technically readable to allow QA Dashboards, Reporting and EVA Calculation

BIG GANT
50%

Better as structure gantt, but missing inline editing feature and the prompt changes in jira issues types lead to a slower workflow as wbs gantt chart.

WBS GANTT CHART
100%

Best Performance: After fast initial load, all changes are done in memory until the “Save” button is pressed.

STRUCTURE GANTT
0%

Work with our plan (3500 wbs tasks in 10 levels) was no more reliable. we have stopped working with the structure gantt.

Allow Instruments to “Control” the Progress of WBS/Plan: Status, Grade of Completion, Estimated End Date, Efforts…

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
100%

Ressource Planning: 1..n Resources with different Loads (Planned Efforts vs Duration)

BIG GANT
50%

Team assignment ist possible.
A team consists of x receivers with independent capacity pattern, a team can be assigned a task. Task may have specific skill requirements defined in the team definition.

WBS GANTT CHART
25%

Only 1:1 assignment

STRUCTURE GANTT
30%

Bulk shift of several WBS Elements directly in WBS Plan e.g. 3 Months later

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
0%

Bulk Change of Attributes of selected WBS Elements

BIG GANT
0%
WBS GANTT CHART
100%
STRUCTURE GANTT
0%

Bulk Copy of a WBS Sub-Tree

BIG GANT
0%
WBS GANTT CHART
0%
STRUCTURE GANTT
100%

Import MS Project Plans

BIG GANT
100%
WBS GANTT CHART
100%
STRUCTURE GANTT
0%

LINKS

Table of contents
    Add a header to begin generating the table of contents

    Categories

    Search

    Mastering projects, made easy: Discover the power of our Jira apps!

    OUR JIRA APP's

    Create and Link

    From $0 / per month

    Try it Now

    Issue PickerS

    From $0 / per month

    Try it Now

    ETL for Reporting

    From $10 / per month

    Try it Now

    ADVANCED LINKS

    From $2.45 / per month

    Try it Now

    FLOATING LICENSES

    From €300 / per year

    Jira Server / Data Center

    Behaviors Builder (24H2)

    From $0 / per month

    Jira Cloud

    More Posts